Here are the pics *finally*:
First, digging the hole - 36" deep, belled out at the bottom for foundation
pouring concrete in teh foundation
forms for the pad
finished pad - cured for a week
third wall goes up, they were built off-site and trucked in, 4 walls up in 1 hour
built the roof from scratch, but all rafters etc were pre-cut to exact lengths
finishing up
Whole garage (not including concrete) completed in 3 hours - yes, 3 hours.
Then I did the electrical myself, and that's as far as I've gotten.
First, digging the hole - 36" deep, belled out at the bottom for foundation
pouring concrete in teh foundation
forms for the pad
finished pad - cured for a week
third wall goes up, they were built off-site and trucked in, 4 walls up in 1 hour
built the roof from scratch, but all rafters etc were pre-cut to exact lengths
finishing up
Whole garage (not including concrete) completed in 3 hours - yes, 3 hours.
Then I did the electrical myself, and that's as far as I've gotten.